ON THE GREEN: BRIDGES UP FOR COMMENT
Bridge-crossing local residents, commuters and others get to weigh in on matters concerning a couple of drawbridges on the Greater Red Bank Green in coming weeks.
Bridge-crossing local residents, commuters and others get to weigh in on matters concerning a couple of drawbridges on the Greater Red Bank Green in coming weeks.
Todd Thompson, seated at center, discussing bridge options with other attendees at the Rumson session. (Photo by John T. Ward. Click to enlarge)
By JOHN T. WARD
What should be done about the crumbling Oceanic Bridge between Rumson and Middletown?
Area residents were offered dozens of options Tuesday as Monmouth County officials hit the reset button on an earlier process derailed by a change in federal regulations.
The Oceanic Bridge between Rumson and Middletown is in “critical” condition, according to the Monmouth County Engineer’s office, and officials plan to unveil “conceptual alternatives” for its replacement or repair at meetings slated in each town today.
Boaters and kayakers shared the Navesink River with a construction barge at the Oceanic Bridge on Monday, Memorial Day. The 75-year-old span, which links Rumson and Middletown, was scheduled to close to all but marine traffic starting at 6 a.m. Tuesday for repairs to the steel bascule.
During repairs in April, deterioration was discovered in two areas of the bascule not previously accessible, Monmouth County officials said last month. The latest repairs are expected to wrap up with a reopening of the bridge on Saturday, June 13. In the meantime, seasonal rules and scheduling will be in effect for marine traffic. (Photo by Peter Lindner. Click to enlarge)
The 75-year-old span will be closed to all but marine traffic for three weeks starting May 26. (Photo by John T. Ward. Click to enlarge)
By JOHN T. WARD
Previously unseen deterioration on the Oceanic Bridge between Rumson and Middletown will require a full shutdown of the span for three weeks following Memorial Day, Monmouth County reported Wednesday.
Overnight closures of the Oceanic Bridge between Middletown and Rumson are scheduled to begin Tuesday night as ongoing repair work to the 75-year-old span continues, according to Monmouth County officials.
Traffic will be shut down from 10:30 p.m. to 6:30 a.m., Sunday through Friday morning, until April 30. A routine of single-lane closures during the day is already in effect to enable the contactor, George Harms Construction Company of Howell, to perform required work above and below the bridge deck, according to a county press release. (Photo by John T. Ward. Click to enlarge)
A 2012 photo of the Oceanic Bridge surface. (Photo by John T. Ward. Click to enlarge)
The Oceanic Bridge between Rumson and Middletown will undergo repair work starting next week that will entail single-lane operation during the daytime and overnight closures until mid-April, the Monmouth County government announced Friday afternoon.